forceten.typepad.com > Velodrome

Wanye and Garth Concrete, Inc. SCHWING!

Wanye and Garth Concrete, Inc. SCHWING!

It is sexy watching them pump concrete to the new track surface, though. SCHWING!


The Boss shows up

The Boss shows up

Never one to shrink away from supervising, EPVA Prez Pete shows up to PLOCK - (Plan Lead Organize Control Kill time).


Still hard work though...

Still hard work though...

There's still a lot of hard work though. Moving real thick concrete around on a slope - Fun!


Easier than Before

Easier than Before

One of the challenges is getting concrete to stay still on a 37° bank. Modern concrete has admixtures that makes this easier.


Hey, Waitaminute!

Hey, Waitaminute!

This was the surprise of the day - they're pouring 'crete!


Day_20_09

Day_20_09


Day_20_08

Day_20_08


Day_20_07

Day_20_07


Day_20_06

Day_20_06


Day_20_05

Day_20_05


Day_20_04

Day_20_04


Day_20_03

Day_20_03


Day_20_02

Day_20_02


Day_20_01

Day_20_01


Day_17_06

Day_17_06


Day_17_05

Day_17_05


Day_17_04

Day_17_04


Day_17_02

Day_17_02


Day_17_01

Day_17_01


Day_14_06

Day_14_06


Day_14_05

Day_14_05


Day_14_04

Day_14_04


Day_14_03

Day_14_03


Day_14_02

Day_14_02


Day_14_01

Day_14_01


Day_12_riprap_on_south_side_of_stream

Day_12_riprap_on_south_side_of_stream

Here's an overview of the rip rap installation - that's a lot of stone!


Day_12_going_over_the_plan

Day_12_going_over_the_plan

The site foreman, engineer, and one of the workers go over the site plan.


Day_12_its_broke

Day_12_its_broke

Hard to move rock when your trackhoe's broke. The man I talked to (Greg) said it just wouldn't start. Dieselitis...


Day_12_tree_removed_02

Day_12_tree_removed_02

Overview of the work area with the tree on the north side of the stream having been removed. Work is progressing very rapidly now.


Day_12_tree_removed_01

Day_12_tree_removed_01

The tree is gone, rip rap installation on the north side of the stream has started, and the second outflow pipe is in place. Engineers, concrete company foremen, and the site foreman go over the plan for the rest of the repair.


Preparing_for_tree_removal_04

Preparing_for_tree_removal_04

Another view as the crane is set up. Unfortunately, I was unable to stay long enough to take pictures as the tree came down.


Closeup_of_cracked_wall_and_repairs_04

Closeup_of_cracked_wall_and_repairs_04

One of the outflow pipe extensions has been installed, as the mattress block installation continues.


Riprap_installation_on_south_side_of_str

Riprap_installation_on_south_side_of_str

The rip rap installation on the souh side of the stream, substantially complete.


Closeup_of_cracked_wall_and_repairs_03

Closeup_of_cracked_wall_and_repairs_03

A good view of the rip rap installation on the south side of the stream.


Overview_of_work_area_03

Overview_of_work_area_03

Overview of the work area, with a better view of the south side reinforcement installed in the area shown excavated in previous photos.


Closeup_of_cracked_wall_and_repairs_01

Closeup_of_cracked_wall_and_repairs_01

Another view of the area prior to tree removal.


Overview_of_work_area_01

Overview_of_work_area_01

The work area prior to tree removal.


Preparing_for_tree_removal_03

Preparing_for_tree_removal_03

It's a big tree, so you need big tree removal equipment...


Preparing_for_tree_removal_02

Preparing_for_tree_removal_02

Another view of the north side of the streambed, and the doomed tree.


Preparing_for_tree_removal_01

Preparing_for_tree_removal_01

The tree shown in this photo will be removed to make way for the rip rap installation on the north side of the stream. It's a shame it has to go, but it is part of the problem!


Closeup_view_looking_upstream_at_wall_an

Closeup_view_looking_upstream_at_wall_an

Another view of the mattress block installation.


View_looking_downstream_at_first_check_d

View_looking_downstream_at_first_check_d

This view is looking west from the outflow area, with the first check dam and construction area in view. As you can see, the check dams serve a valuable purpose to help reduce siltage downstream.


View_of_partial_matressing_installation

View_of_partial_matressing_installation

Another view of the mattress blocks being placed.


View_looking_down_at_outflow_with_rip_ra

View_looking_down_at_outflow_with_rip_ra

Rip rap and mattressing blocks are placed in the streambed to form a good base for the outflow pipe extensions.


Excavation_on_south_side_of_stream_02

Excavation_on_south_side_of_stream_02

This view shoes the end of the existing wall, which will be reinforced with new construciton.


Excavation_on_south_side_of_stream_01

Excavation_on_south_side_of_stream_01

This area was excavated to make way for the installation of the riprap, which will prevent erosion under the new wall reinforcement.


Construction_entrance_extension

Construction_entrance_extension

One issue we ran into was the City's dissatisfaction with the construciton entrance - despite their buy-off on the site plan. The city is never one to let a prior agreement stand in the way of Bureaucracy.


Repair_materials_02

Repair_materials_02

Close-up of the mattressing blocks, which are basically interlocking concrete blocks.


Repair_materials_01

Repair_materials_01

This is the mattressing material that will be placed in the streambed, both under the new outflow pipes and out into the new wash area, to prevent erosion of the streambed. Streambed erosion was what led to the cracking of the original retaining wall.


Outflow_pipe_extensions_01

Outflow_pipe_extensions_01

These are the pipe extensions that will be placed in the existing outflow area. Once in place, rubble and riprap will be compacted around them, and concrete poured to hold them in place. This will form part of the new reinforcing system for the old wall.


»